                        Project goals for spring quarter

 

S P H I N X   T E A M
April 22, 2002

 

 

 

               .

 

 

 

Target
Date
Revised Date Milestone Description Done
01/14/02
01/14/02
01/28/02
02/12/02
02/12/02
03/01/02
03/14/02
03/14/02
04/15/02
04/15/02
04/15/02
04/29/02
04/29/02
04/29/02

01/14/02
01/14/02
01/28/02
02/12/02
02/12/02
03/01/02
03/14/02
04/29/02
04/22/02
04/29/02
04/29/02

Set up Mac workstation in ACC
Write specs for 1st release
Create use cases and user profile
Create semi-functional GUI
Create screen shots to review with Kelly
Make tech. decision: Swing Vs. Cocoa
Give project presentation to class
Integrate GUI with Backend
Complete backend functionality
Add Outliner node operations
Outliner component finished
Mapper displays map from XML
Global application GUI functional
Outliner

100%
100%
100%
100%
100%
100%
100%
80%
100%
85%
80%
0%
15%
?%