Individual Status Report

Name: Steve Lynch

Date: 04-29-02

Accomplishments for week 4:

- I've got a simple Wireframer and Mapper done.
- I decided I'd get down and dirty this week, I wanted to get the Wireframer
out the door so I could get busy on some other things, namely the Mapper. I
have a crude wire framer "done" but as is the nature of the beast I could
add features forever.
- The Mapper went very smoothly but I'll need to document some code, it's a beast but it works... well.

Objectives for week 5:

- There are some small things that bug me about both the Mapper and the wire
framer I'll try to put my finger on. I would love to be able to select lots
of screen components by drawing a box around them and be able to scale
images on the screen.
- Or I could finish off an Applet as a simple deliverable by making a whatever
Geoff and Alex have been working on, what's it called?

Issues/Bugs

- All this junk is kept in memory I'll need Geoff's help probably to make a
file reader/writer that spits out XML
- I'm spending too much time in the lab.