                        Project goals for spring quarter

 

S P H I N X   T E A M
May 13, 2002

 

 

 

 

 

Target
Date
Revised Date Milestone Description Done
Ongoing Testing suite for backend and Outliner 10%
05/13/02 05/20/02 Both components work under main app. GUI 10%
05/13/02 05/20/02 Mapper and Outliner fully integrated 20%
05/13/02 05/20/02 Mapper can modify nodes and save results 5%
04/29/02 05/20/02 Global application GUI functional 70%
04/29/02 05/20/02 Mapper displays map from XML 35%
04/15/02 04/29/02 Outliner component finished (completed to revised minimum functionality. Could still be improved) 100%
04/15/02 04/29/02 Add Outliner node operations 100%
04/15/02 04/22/02 Complete backend functionality 100%
03/14/02 04/29/02 Integrate GUI with Backend 100%
03/14/02 03/14/02 Give project presentation to class 100%
03/01/02 03/01/02 Make tech. decision: Swing Vs. Cocoa 100%
02/12/02 02/12/02 Create screen shots to review with Kelly 100%
02/12/02 02/12/02 Create semi-functional GUI 100%
01/28/02 01/28/02 Create use cases and user profile 100%
01/14/02 01/14/02 Write specs for 1st release 100%
01/14/02 01/14/02 Set up Mac workstation in ACC 100%