MILESTONES,
week 6
Project goals for spring
quarter
| Target Date |
Revised Date | Milestone Description | Done |
| Ongoing | Testing suite for backend and Outliner | 10% | |
| 05/13/02 | 05/20/02 | Both components work under main app. GUI | 10% |
| 05/13/02 | 05/20/02 | Mapper and Outliner fully integrated | 20% |
| 05/13/02 | 05/20/02 | Mapper can modify nodes and save results | 5% |
| 04/29/02 | 05/20/02 | Global application GUI functional | 70% |
| 04/29/02 | 05/20/02 | Mapper displays map from XML | 35% |
| 04/15/02 | 04/29/02 | Outliner component finished (completed to revised minimum functionality. Could still be improved) | 100% |
| 04/15/02 | 04/29/02 | Add Outliner node operations | 100% |
| 04/15/02 | 04/22/02 | Complete backend functionality | 100% |
| 03/14/02 | 04/29/02 | Integrate GUI with Backend | 100% |
| 03/14/02 | 03/14/02 | Give project presentation to class | 100% |
| 03/01/02 | 03/01/02 | Make tech. decision: Swing Vs. Cocoa | 100% |
| 02/12/02 | 02/12/02 | Create screen shots to review with Kelly | 100% |
| 02/12/02 | 02/12/02 | Create semi-functional GUI | 100% |
| 01/28/02 | 01/28/02 | Create use cases and user profile | 100% |
| 01/14/02 | 01/14/02 | Write specs for 1st release | 100% |
| 01/14/02 | 01/14/02 | Set up Mac workstation in ACC | 100% |