Sphinx Project Progress Report: Week 6

 

Meeting Attendance:

Monday: Randy, Geoff, Alex, & Kate

Tuesday: no meeting

Wednesday: Alex, Steve, Geoff & Randy

Thursday: Alex, & Randy

Friday: Geoff & Randy

Saturday: Geoff, Alex

 

Deliverables:

Randy: Report to Kelly - Yes

Alex: Meeting Agenda - No

Geoff: Millstone report - Yes

Steve: Current state of GUI screenshot - No

 



Issue 18: Time to think about integration again. Need to work Steve's accomplishments into the Milestone Overview.


Status: Integration was not possible last week because Steve left town without telling us and without giving us a copy of his code. This week, we meet on Wednesday night, but the V: drive was down and we did not have access to our code. I got Isaac to fix the V: drive problem, and our code was intact, but I was not able to attend our scheduled Saturday meeting so I do not know how (or if) things went.



Issue 19: Team meeting times (revisited). We should plan to work as a team Monday, Wednesday, Friday, & Saturday. Need to identify times that work for everybody.

Status: This continues to be a problem. We will discuss this again Monday.



Issue 20: Need to establish CVS procedure.

Status: Alex is working on this. Geoff and Alex seam to have this down, now Steve and I need to get up to speed. There seems to be difficulties (surprise, surprise) getting the CVs software to work on my Mac.