Individual Status Report
Name: Alex Mikitik
Date: 05-20-02
Accomplishments for week 7:
- Integrated Mapper with Outliner & UI Framework.
- Began GUI beatification.
- Fixed various bugs
- Fixed Mapper mousdrag problem
Objectives for week 8:
- Continue efforts to customize UI visual presentation (ie POLISH!).
- Think of an application name.
- Create a basic "About" menu.
Issues/Bugs
- Continue beatification.
- Hook up Wireframer with Mapper/Outliner.