Sphinx Project Progress Report: Week 7

 

Meeting Attendance:

Monday: Randy, Geoff, Alex, Steve & Kate

Tuesday: no meeting

Wednesday: Geoff, Randy, Alex & Steve

Thursday: Geoff, Alex, & Randy

Friday: Geoff, Randy, Alex & Steve

Saturday: Geoff, Alex, & Randy

Sunday: Geoff & Randy

 

Deliverables:

Randy: Report to Kelly - Yes

Alex: Meeting Agenda - Yes

Geoff: Millstone report - Yes

Steve: Current state of GUI screenshot - No

 



Issue 18: Time to think about integration again. Need to work Steve's accomplishments into the Milestone Overview.


Status: Integration of Outliner & Mapper to XML backend was sucessfull. Still need to integrate the WireFramer.



Issue 19: Team meeting times (revisited). We should plan to work as a team Monday, Wednesday, Friday, & Saturday. Need to identify times that work for everybody.

Status: Meeting were well attended and productive all week (mostly).



Issue 20: Need to establish CVS procedure.

Status: Team has been using CVS effectvly.