Sphinx Project Progress Report: Week 8

 

Meeting Attendance:

Monday: Geoff, Alex, Steve & Kate

Tuesday: Geoff, Randy, Alex & Steve

Wednesday: Geoff, Randy, Alex & Steve

Thursday: Geoff, Randy, Alex & Steve

Friday: no meeting

Saturday: no meeting

Sunday: no meeting

 

Deliverables:

Randy: Report to Kelly - Yes

Alex: Meeting Agenda - No

Geoff: Millstone report - Yes

Steve: Current state of GUI screenshot - No

 



Issue 18: Time to think about integration again. Need to work Steve's accomplishments into the Milestone Overview.


Status: Integration of Outliner & Mapper to XML backend was sucessfull. Still need to integrate the WireFramer.



Issue 21: Need to prepare demonstration for Kelly. How are we going to deliver.

Status: Right now we can demonstrate the product using Randy's laptop.