MILESTONES,
week 9
Project goals for spring
quarter
| Target Date |
Revised Date | Milestone Description | Done |
| Ongoing | Testing for Outliner, Mapper, & WireFramer | 50% | |
| 05/24/02 | 06/04/02 | Application prototype completed | 95% |
| 04/29/02 | 06/04/02 | Global application GUI functional | 90% |
| 06/02/02 | Pending* | All three components work under main app. GUI | 75% |
| 06/02/02 | Pending* | WireFramer fully integrated | 20% |
| 06/02/02 | Pending* | WireFramer displays from XML | 0% |
| 06/02/02 | Pending* | WireFramer component finished (completed to revised minimum functionality) | 40% |
| 05/24/02 | 06/04/02 | Mapper tree drawing algorithm finalized | 95% |
| 05/13/02 | Pending* | Mapper can modify nodes and save results | 35% |
| 05/13/02 | 05/20/02 | Both components work under main app. GUI | 100% |
| 05/13/02 | 05/20/02 | Mapper and Outliner fully integrated | 100% |
| 04/29/02 | 05/20/02 | Mapper displays map from XML | 100% |
| 04/15/02 | 04/29/02 | Outliner component finished (completed to revised minimum functionality. Could still be improved) | 100% |
| 04/15/02 | 04/29/02 | Add Outliner node operations | 100% |
| 04/15/02 | 04/22/02 | Complete backend functionality | 100% |
| 03/14/02 | 04/29/02 | Integrate GUI with Backend | 100% |
| 03/14/02 | 03/14/02 | Give project presentation to class | 100% |
| 03/01/02 | 03/01/02 | Make tech. decision: Swing Vs. Cocoa | 100% |
| 02/12/02 | 02/12/02 | Create screen shots to review with Kelly | 100% |
| 02/12/02 | 02/12/02 | Create semi-functional GUI | 100% |
| 01/28/02 | 01/28/02 | Create use cases and user profile | 100% |
| 01/14/02 | 01/14/02 | Write specs for 1st release | 100% |
| 01/14/02 | 01/14/02 | Set up Mac workstation in ACC | 100% |
* Continuation and completion of project pending agreement with Blink Interactive
architects.